Brandon Scott: “I wasn’t even in school when some of these bridges were put in this condition”
The mayor responds to questions about lead paint chips flaking off three Baltimore bridges, which is costing the city $1.5 million to pick up off the ground
Above: Baltimore Mayor Brandon Scott at the November18 press availability, flanked by DPW Director Matt Garbark and City Administrator Faith Leach. (CharmTV)
Mayor Brandon Scott was asked today about $1.5 million in emergency contracts quietly allocated by the Department of Transportation to address the lead paint flakes that suddenly fell from three Baltimore bridges last winter during a sharp temperature drop.
“What we have to understand is that we’re talking about – these bridges being painted with the chips that you’re talking about – happened before I was 10 years old,” Scott said, at today’s post-Board of Estimates (BOE) press availability.
The expenditure, listed on the routine agenda as emergency spending to be “noted,” was approved without comment or discussion by Scott and the rest of the board.
The spending, initially presented as $20,000, had been deferred from the agenda last month and was subsequently revealed, after Brew inquiries, to total $1,550,274.40 – or 77 times that amount.
The “emergency procurement included $765,000, which only covered picking up the orange-colored chips that had blanketed the ground below the three bridges in February – a task completed over a few weeks in June.
(For comparison, the State Highway Administration removed toxic lead chips that fell off three of its bridges, but did the work for just $200,000, The Brew story also noted.)
• Initially presented as $20,000, cost of picking up lead paint flakes below three city bridges now set at $1.5 million (11/18/26)
• Flaking orange paint from the 28th Street Bridge is littering Falls Road and the Jones Falls (2/7/26)
• Paint flakes falling from 28th Street Bridge contain lead and are hazardous, MDE says (2/20/26)
• Two more Baltimore area bridges confirmed to be shedding lead paint flakes (3/3/26)

The 28th Street Bridge that crosses the Jones Falls, Falls Road and Jones Falls Trail last month with paint still peeling. (Mark Reutter)
Brew reporting revealed that the rest of the spending – $785,137 – only covers picking up whatever flakes fall between now and September 2027.
It does not cover the remedy needed to stop the falling flakes at the source – scraping off the hazardous lead paint on the bridges and repainting.
(Again for comparison, The Brew noted that eight state-owned bridges that shed toxic paint during that same February cold snap have already been repainted.)
“We have a lot of traffic maintenance issues that . . . [adds] a great deal to the cost of doing business in the city” – Deputy Mayor Khalil Zaied.
“The deputy mayor [Khalil Zaied] will go into the details,” Scott said, assuring reporters that his administration would tackle the paint chip problem “even though I wasn’t even, you know, in school when some of these bridges were put in this condition.”
Zaied said the $1.5 million expenditure was a short-term strategy being pursued while the city works with the SHA on “long-term” full remediation, meaning a contract to cover scraping and repainting the bridges.
When a reporter pressed him to explain why SHA paid so much less for its clean-up of falling paint chips, Zaied protested that comparing state costs with city costs was not fair.
“The extent of work that is needed to be done requires so many different things, the mobilization in certain areas within an urban region,” he said, adding:
“We have a lot of traffic maintenance issues that we have to take care of that [adds] a great deal to the cost of doing business in the city.”